Client: McNab Constructions Pty Ltd
Project: Aldi Foodstore, Gatton
Duration: July 2008 to December 2008
Project Value: $780,000
Project Details: Our contract was to strip the site including tree removal, excavate approx 1.5m into the existing sub grade and remove from site, import approx 15,000m3 of CBR15 material place and compact under level 1 supervision, full pavement construction for the 45 space car park with asphalt, underground detention tank and full installation of a Humes STC3 GPT. This project also had a Main Roads turn in lane of a major intersection with deep lift asphalt construction and Lockyer Regional Council storm water upgrades adjacent to the new Aldi Store.
Well the New Year is in full swing and with it has come plenty of rain. The rain is fantastic for all the new turf that has been laid at Nudgee College and Les Hughes Sports Complex. These projects are both coming into the final stages of construction whilst construction at Griffin Sports Facility is ramping up despite the recent weather. We have also been awarded two new projects in the new year. One is Sports field lighting upgrades at 3 locations within the Moreton Bay Regional Council area and the second is goal upgrades to various sites for Redland City Council whom we are excited to be working with again.
23 February 2021